Cascade Vista Phase 1 AC Water Main Replacement

Project Details

The scope of work for construction consists of the replacement of approximately 5,900 linear feet of end-of-lifecycle 4-inch, 6-inch, and 8-inch diameter asbestos-cement (AC) water main with 4-inch and 8-inch diameter ductile iron (DI) water main. The project includes installation of new fire hydrants, miscellaneous valves, water service lines, and meter boxes from the new water main to the customer line, including tie ins.

Project Benefits

  • Fewer leaks and breaks
  • Enhanced water quality
  • Better fire protection flow
  • Reduced maintenance costs
  • Lower risk of water service interruptions

Schedule

  • April 2026 - Construction Start
  • October 2026 - Construction End

What to Expect During Construction

  • Equipment noise
  • Construction traffic
  • Street detours with local access
  • Driveway and pedestrian access restrictions
  • Temporary water service interruptions during construction
  • Properties directly affected will be notified in advance

Questions? Contact the District Office at 253-630-9900 or customer_service@sooscreek.com