|
Deficiencies in the existing west sewer
forcemain at the District's Lift Station (LS) #5B necessitate
replacement of the sewer forcemain. The existing 12-inch
ductile iron forcemain is approximately 4,000 feet long
and ties into a gravity system located in SE 196th Street.
The deficiencies in the pipe include severe pitting at the
bottom of the forcemain pipe, causing the pipe integrity
to be compromised. The District has decided to replace the
4,000 feet of existing sewer forcemain with 18-inch and
12-inch HDPE forcemain. The proposed 18-inch HDPE sewer
forcemain replacement will start at existing LS #5B, then
west in SE 198th Place, and then north in 124th Avenue SE
to SE 196th Street. At that point, a 12-inch HDPE sewer
forcemain will extend west along SE 196th Street with connection
to the existing gravity sewer manhole located west of 119th
Avenue SE.
This project is scheduled to begin construction
in June 2009 and be completed by October 2009.
|
|
This project began construction in the
June of 2008. The 6" and 8"asbestos concrete water main
around the lake was installed in 1965; it was replaced with
8" ductile iron pipe, new water service lines, valves and
fire hydrants. Along with this replacement, the District
installed a low pressure grinder pump system to convey sewage
to an existing gravity sewer system.
Upon completion of this work the roads
around the lake were overlaid.
|
|
This project would replace approximately
10,900 feet of 6 inch AC pipe with 8 inch ductile iron and
approximately 300 ft of 4 inch AC pipe with 4 inch ductile
iron in the Cascade Vista area. The pipes were installed
between 1950 and 1961 and have reached the end of their
useful life. We have had several breaks in the area and
have inspected the pipe at numerous locations. We have determined
that the pipe is soft and needs to be replaced.
This project is just starting design and
should start construction in early 2010.
|